Major Amendment 14 Timeline
March 2026, Internal Scoping and Application Review: After receiving a final application from Sibanye-Stillwater, DEQ will review it for completeness and make a preliminary determination on the required level of MEPA review.
May 2026, Public Notification: DEQ informs the public and other agencies about the proposed project and the intent to prepare an EA or EIS, through press releases and the DEQ website.
May 2026, Public Scoping Period: A formal period is established (typically 45-60 days) during which the public can submit comments, concerns, and ideas. DEQ collects comments in various forms, including written submissions (mail, email), online forms, and oral comments at public meetings.
May 2026, Scoping Meetings: Public scoping meetings are often held to educate the public about the project, provide an overview, and solicit input. At these meetings, DEQ records public concerns and ideas about potential impacts and alternatives. These meetings can be in-person or virtual.
June 2026, Comment Analysis and Summary: After the scoping period closes, DEQ analyzes and summarizes the comments received. The substantive issues identified during scoping guide the preparation of the draft environmental document.
TBD 2027, Addressing Issues in the Draft EIS/EA: The environmental document will address each substantive issue and evaluate a range of alternatives and potential mitigation measures. Note, you generally must comment during the Draft EIS phase to ensure your input is formally addressed in the Final EIS, as the Final EIS must respond to substantive comments from the Draft EIS, but does not usually open new comment periods.